Uisce Éireann steps up reservoir cleaning across Louth

Tullyallen Reservoir Cleaning Finalisedplaceholder image
Tullyallen Reservoir Cleaning Finalised | Supplied

Crews have been working across 30 treated reservoirs in Louth

Uisce Éireann has said that its Reservoir Cleaning Programme is gaining strong momentum across Louth, with “significant progress already delivered and a clear plan in place to safeguard water quality and supply reliability for communities.”

Since March, crews have been working across 30 treated reservoirs of varying sizes, ranging from large Olympic-scale pools to smaller local assets.

To date, 13 reservoirs have been fully deep cleaned, with a further 17 on track for completion by October as part of a managed programme of works.

In a statement Uisce Éireann said: “At its core, the programme is focused on key benefits: maintaining the highest standards of safe, clean drinking water for communities and strengthening the resilience of the water network to support a consistent supply. This essential maintenance is designed to remove sediment build-up, prevent contamination, and maintain compliance with drinking water quality standards.

“This complex work is underpinned by detailed planning and a phased delivery approach that ensures customers continue to receive a continuous water supply throughout the works rather than taking reservoirs offline abruptly. Treated reservoir levels are carefully reduced through normal customer usage before specialist crews carry out intensive cleaning, inspection and disinfection works.”

Peter Liggett, Project Manager with Uisce Éireann, highlighted the precision and coordination involved.

“Our customers are at the forefront of this programme, and a phased approach has been carefully planned throughout the eight-month delivery period.

“Significant planning is required for each reservoir, including carefully sequencing activities, scheduling works during off-peak demand, and managing network flows to allow supply to be supported from alternative zones where needed. In instances where interruptions are unavoidable, works are carried out at night to minimise impact on customers.”

An example of this approach in action is the recent deep clean of the Donore treated water reservoir.

Although located across the border in Meath, it is a critical asset supplying Drogheda.

This twin-cell treated reservoir plays a vital role in meeting the area's high-water demand, supplying approximately 65,000 litres per hour.

Each reservoir measures 32.2 metres in diameter and 6.5 metres in height. Together, they have a combined capacity exceeding two Olympic-sized swimming pools.

The first treated reservoir was gradually drawn down through normal customer demand, enabling specialist crews to remove naturally occurring sediment using advanced jet‑vac equipment. Cleaning, inspection and disinfection were completed within four hours, while the second reservoir remained fully operational—ensuring uninterrupted supply to customers.

Once complete, the cleaned reservoir was carefully refilled over a controlled period before the team switched focus to the second reservoir, repeating the same efficient process.

The treated water reservoirs at Ardee–Blakestown and Tullyallen have both recently been cleaned as part of this programme.

James O’Hagan, Water Network Operations Manager said: “While reservoir cleaning works are progressing at pace, customers may experience occasional short-term discolouration as network conditions adjust. This is temporary and typically resolves once normal network flows stabilise.”

Throughout July, works will focus on multiple tanks and reservoirs within the Cavanhill Water Treatment Plant. Upon completion of these works, the programme will move to the reservoirs serving Termonfeckin and Clogherhead before progressing north to all active reservoirs across the Collon, Ardee and Cooley water supply networks.

The programme is scheduled for completion by late October 2026 and will ensure that all active reservoirs across the county have been cleaned and inspected.