Carlingford Greenway link from Victoria Lock to border can be delivered on time says Council


Louth County Council January meeting
Louth County Council believes that the project to extend the Carlinglough Greenway, from Victoria Lock in Newry to the Border, can be delivered within the timeframe available, despite reports that there was a setback to the project due to changes to part of the planned route.
Cllr Antóin Watters sought an update on the greenway at the Louth County Council January meeting, mentioning reports in the press in Northern Ireland about the setback, and asked if the Council was happy that the issue wouldn't affect the project as a whole.
According to the Enterprise, Regeneration & Tourism Committee of Newry, Mourne and Down District Council, the planning notice submitted in August 2020 sought to use the old railway/county road on the landward side of the Fathom line between Victoria Lock and the Border.
Proposals for two uncontrolled road-crossing points at Victoria Lock and the Border, and a speed reduction request to allow for them was made to the Department for Infrastructure (DfI). This was not permitted by the DfI however, and alternative route design options were then developed, with the new preferred route option now submitted to the Special EU Programmes Body (SEPUB) for consideration.
The amended route changes, according to the Committee, requires alteration to the scheme design and the preparation of a new planning application pack which will be submitted in early 2023.
In response to Cllr Watters' query regarding any potential delays to the project, Chief Executive of Louth County Council, Joan Martin, told the meeting that she has attended a considerable number of meetings on the project and that the Council believes that the project can be delivered within the timeframe available.
The Chief Executive added that the Council has secured the grant for the project and continues to seek additional funding to bring it to completion.